The Capital Engineering branch is responsible for various engineering projects throughout the Town of East Gwillimbury (EG), outside of new development/unassumed areas.
To view the Road Construction and Capital Engineering projects check out our Interactive Map.
Project descriptions and frequently asked questions (FAQ's) are provided for the following Capital Engineering projects:
Mount Albert Storm Outfalls, Retaining Wall and Trail Design |
Project Background: This storm outfall and retaining wall project is in the community of Mount Albert, adjacent to Vivian Creek Park. There are four storm outfalls and one span of retaining wall in need of repair. Town staff have investigated and continue to monitor the condition of the outfalls, although they require repair, the current state is stable and interim holding repairs will be completed (if necessary) until construction takes place. Similarly, the slope behind 13 and 15 Valley Mills Road was also inspected, monitored, and deemed stable. Vivian Creek Trail Feedback Thank you to everyone who completed the Vivian Creek Trail Closure survey. Your thoughts and feedback have been incorporated into a staff memo for Council. The memo was presented to Committee of the Whole on July 25, 2023, to view the Agenda, please visit the Council meeting portal.
Retaining Wall Location:
The map below outlines the retaining wall and storm outfall locations. This project has several complex Next Steps:
Project Notices: Council Reports and Memos: |
Asphalt Resurfacing & Reconstruction |
Construction has been completed at the following locations in 2024:
The following locations have been rescheduled for 2025:
|
Road Reconstruction Design |
The following locations have detailed designs that are nearly complete:
A public information centre (PIC) was held on Wednesday, December 6, 2023. Project maps and PIC presentation materials are below for your reference: Questions? If you have feedback or questions for the project team, please contact them by email.
|
Bridge Rehabilitation - Design and Construction |
DesignThe following locations have detailed designs that are complete:
The following locations have detailed designs that are underway:
ConstructionThe following locations have construction and utility relocations that are underway:
|
Micro-Surfacing |
Micro-surfacing construction work has been completed at the below locations during 2024. As part of this road work, curb and sidewalk repairs were also completed. Queensville:
Holland Landing:
Mount Albert:
Sharon:
Community UpdatesQueensville - Microsurfacing scheduled for late September/ early October. Holland Landing - Microsurfacing scheduled for late September/ early October. Mount Albert - Microsurfacing completed, pending road sweeping and stop bar painting. Sharon - Microsurfacing 80% completed, pending road sweeping and stop bar painting.
What is micro-surfacing?It is a versatile and efficient solution for maintaining and improving road quality, ensuring a smooth and durable surface for drivers. Micro-surfacing extends the life of the road surface, saves future construction costs, and has less impact on the environment than other road treatment options. Residents may experience temporary road and lane closures during work and are asked to limit parking on the above roads to assist crews. Residents may initially experience road roughness and loose fine stones prior to road sweeping. Thank you for your patience and cooperation as we complete this important road work.
Project Notice: |
New Sidewalk Construction |
The following location is scheduled for new sidewalk construction:
Construction contract preparation underway, construction expected late 2024/ early summer 2025.
|
New Sidewalk Design |
The following locations currently have designs underway:
|
Miscellaneous Concrete Repairs (Sidewalks & Curbs) |
Various locations throughout Town, identified through annual inspections.
|
Streetlight Pole Rehabilitation |
Steel streetlight poles identified for repair and replacement through inspections completed in 2023/ 2024.
|
Master Plans |
Downtown Mount Albert Revitalization |
Yonge Street Revitalization |
New Multi-Use Path and Lighting |
The following limits have a completed detailed design:
The following are approved construction limits:
Council Memos and Reports
Public Information Centre (PIC) Thank you to everyone who attended the joint PIC on June 28, 2023 at the Holland Landing Community Centre. Proposed project layouts are below for your reference: Questions? If you have feedback or questions for the project team, please contact them by email.
|
Water Rehabilitation Program |
A Sharon watermain replacement detailed design is underway for the following locations:
A new watermain design of a secondary watermain connection for the West Holland Landing community (west of Holland Landing Road).
nstallation of new fire hydrants at strategic locations:
|
Once the individual construction projects above are awarded, a copy of the Notice of Work will be uploaded into the table for reference.
For more information on current and upcoming regional construction projects in East Gwillimbury, please visit York Region's website.
The Government of Canada provides funding to Municipalities with Gas Tax Funding for a variety of different project categories including local roads and bridges. From the Town's Capital Budget, the following Road Construction and Capital Engineering projects have received this funding:
Road Rehabilitation Program
Miscellaneous Concrete Rehabilitation
East Townline Bridges - Rehabilitation
Click the puzzle pieces to learn more about this project.
for members of the public to review and provide feedbackOur Customer Service Team is here to help!